Mixing Valves

Detail ID 7.0303.1
Topic
Water Heating
Subtopic
Distribution Components
Desired Outcome

Safe and reliable water temperature control

SF Single Family Site-Built Housing
MH Manufactured Housing
MF Multifamily Housing

Specifications

  • SF
  • MH
  • MF
Specification Objective

Verify current plumbing infrastructure is sufficient to support the installation(s) and is leak-free

Verify adequacy of plumbing

  • SF
  • MH
  • MF
Specification Objective

Install mixing valves at as many locations as necessary to deliver safe and adequate hot water

Optimal water temperature throughout the system

  • SF
  • MH
  • MF
Specification Objective

Install equipment in compliance with applicable code (e.g., NFPA 70, IRC, IBC, IMC) and manufacturer specifications

If conflict exists between code and manufacturer specifications, apply the more restrictive requirement

Compliant and safe installation

  • SF
  • MH
  • MF
Specification Objective

Install valve and plumbing to allow for inspection, maintenance, and replacement of the appliance and its components, without disturbing other installed equipment, controls, piping, and components, other than what requires repair/replacement

Ensure the valve can be readily maintained and replaced

  • SF
  • MH
  • MF
Specification Objective

Install a separate water cut-off valve for both the hot and cold incoming water lines

Allow isolation and service of mixing valve

  • SF
  • MH
  • MF
Specification Objective

Install check valves on the hot and cold water supply lines upstream of the mixing valve

Eliminate crossover

  • SF
  • MH
  • MF
Specification Objective

Install mixing valve with a heat trap or at a distance from heat sources sufficient enough to prevent scaling or damage to the valve

Prevent scaling and valve damage

  • SF
  • MH
  • MF
Specification Objective

Install temperature gauges on hot, cold, and tempered supply water lines within sight of the mixing valve

Verification of proper mixing valve operation

  • SF
  • MH
  • MF
Specification Objective

Install controls and sensors in accordance with manufacturer specifications and applicable code (NFPA 70)

When controls are low voltage, separate the low voltage and line voltage wiring

Safe and compliant mixing valve operation

  • SF
  • MH
  • MF
Specification Objective

Install dielectric unions when connecting copper to galvanized steel piping in accordance with the IRC and manufacturer specifications

Prevent corrosion between dissimilar metals

  • SF
  • MH
  • MF
Specification Objective

Set discharge temperature to not exceed 120 degrees or as prescribed by local code

Prevent biological growth in tank but prevent scalding

  • SF
  • MH
  • MF
Specification Objective

Provide occupants/owners with user's manual, warranty information, installation instructions, and installer contact information

Manufacturer supplied information available to occupant

View Sub-Topic:
Distribution Components
Next Detail:
Piping