Version 2020 14/08/2020 - 14:23 4.0103.3d Installation

Install batt insulation to prescribed R-value in full contact with the existing insulation batts without gaps, voids, compressions, or misalignments

If the top of the existing insulation is below the top of the framing, install new batts parallel with framing members

If the top of the existing insulation is above the top of the framing, install new batts perpendicular to framing members

Uniform insulation depth in continuous contact with existing insulation without voids

Black Line
Version 2020 14/08/2020 - 14:23 4.0103.3d Installation

Install batt insulation to prescribed R-value in full contact with the existing insulation batts without gaps, voids, compressions, or misalignments

If the top of the existing insulation is below the top of the framing, install new batts parallel with framing members

If the top of the existing insulation is above the top of the framing, install new batts perpendicular to framing members

Uniform insulation depth in continuous contact with existing insulation without voids