Attic access door safely and durably sealed and insulated to prevent air movement @ 50 Pascals of pressure
Specifications
- SF
- MH
- MF
Specification | Objective |
---|---|
Select sealants that: are compatible with their intended surfaces, allow for differential expansion and contraction between dissimilar materials, meet the requirements of the applicable fire safety code (e.g. thermal or ignition barriers), and for use inside the pressure boundary select low volatile organic compound (VOC) sealants that meet independent testing and verification protocols |
Select safe and effective sealants |
- SF
- MH
- MF
Specification | Objective |
---|---|
Select materials that: adequately support applied load and are permanent air barriers, meet the requirements of the applicable fire safety code (e.g. thermal or ignition barriers), and for use inside the pressure boundary select low volatile organic compound (VOC) materials that meet independent testing and verification protocols |
Select safe and effective materials |
- SF
- MH
- MF
Specification | Objective |
---|---|
Remove any material from the sealing area that will prevent full adhesion of the selected sealant |
Surface is clean and ready to accept sealant |
- SF
- MH
- MF
Specification | Objective |
---|---|
Apply a continuous seal at all seams, cracks, joints, and edges of access framing while applying sufficient pressure to push sealant into any gaps or cracks and contact any backing or infill material required |
Prevent air and moisture movement |
- SF
- MH
- MF
Specification | Objective |
---|---|
Seal access using gaskets, weather stripping or equivalent method Permanently attach gaskets, weatherstripping, etc. per manufacturer's instructions Secure attic door or hatch with a latch, lock or frictionally engaging components |
Prevent air and moisture movement |
- SF
- MH
- MF
Specification | Objective |
---|---|
Install a rigid and durable dam having a height greater than the insulation at attic opening and does not interfere with the operation of the access |
Prevent insulation movement |
- SF
- MH
- MF
Specification | Objective |
---|---|
Insulate access to the same R-value as adjoining insulated assembly Permanently fasten insulation to access in complete contact with the air barrier |
Align thermal barrier |
- SF
- MH
- MF
Specification | Objective |
---|---|
Completed measure will have a minimum expected service life of 20 years |
Ensure minimum service life |