Accessible Attic - Loose Fill Installation

Detail ID 4.0103.2
Topic
Attics
Subtopic
Attic Floors - Unconditioned Attics
Desired Outcome

Continuous, contiguous, safe, and compliant thermal barrier installation

SF Single Family Site-Built Housing
MH Manufactured Housing
MF Multifamily Housing

Specifications

  • SF
  • MF
Specification Objective

Verify that installation area is free of:

active water leaks, fuel leaks (i.e., gas, oil, propane), and pest intrusions

energized or undammed knob and tube wiring

uncovered electrical junctions

improperly terminated devices (ventilation fans, dryers, plumbing stacks, condensate lines, combustion appliance flues/chimneys, etc.)

unshielded high-temperature devices (non-IC rated recessed lights, chimneys, flues, vents, etc.) unless they are zero clearance devices

insulation escape openings

Verify that installation area:

is intact, able to support insulation weight, and air sealed

Ensure space can be safely insulated

  • SF
  • MF
Specification Objective

Select insulation that has a flame spread and smoke development index of 25/450 or less when tested in accordance with ASTM E84 or UL 723

Select fire safe insulation

  • SF
  • MF
Specification Objective

When vented eaves or soffits exist, mechanically fasten insulation baffles in every roof bay that extend above the final insulation level by at least 6"

Install a minimum of one insulation depth marker and one marker every additional 300 ft2 throughout installation area with measurement beginning at the air barrier

Install flags at all utility junctions that can be seen above the final level of the insulation

Protect insulation R-value, provide depth measurement, and locate junctions for future access

  • SF
  • MF
Specification Objective

Install loose fill insulation to prescribed R-value in every joist bay in full contact with the air barrier without gaps, voids, compressions, or misalignments

Continuous and contiguous pressure and thermal barrier of consistent R-value

  • SF
  • MF
Specification Objective

Post a dated receipt signed by the installer that minimally includes: Installed insulation type, coverage area, installed thickness, minimum settled thickness, installed R-value, and number of bags installed

Comply with 16 CFR 460.17 and document contract compliance