Continuous, contiguous, safe, and compliant thermal boundary that prevents air movement @ 50 Pascals
Specifications
- SF
- MH
- MF
Specification | Objective |
---|---|
Verify that installation area is free of: active water leaks, fuel leaks (i.e., gas, oil, propane), and pest intrusions energized knob and tube wiring uncovered electrical junctions improperly terminated devices (ventilation fans, dryers, plumbing stacks, condensate lines, combustion appliance flues/chimneys, etc.) unshielded high-temperature devices (non-IC rated recessed lights, chimneys, flues, vents, etc.) unless they are zero clearance devices insulation escape openings Verify that installation area is: intact, able to support insulation weight, and air sealed (including blockers under kneewalls in alignment with the interior side of the kneewall) |
Ensure space can be safely insulated |
- SF
- MH
- MF
Specification | Objective |
---|---|
Permanently secure existing batt insulation in full contact with the existing air barrier and sides of the existing cavity without gaps, voids, compressions, or misalignments |
Align pressure and thermal boundary |
- SF
- MH
- MF
Specification | Objective |
---|---|
Install airtight backing material in full contact with the existing cavity insulation Secure backing material using mechanical fasteners that penetrate the sub framing a minimum of 1" Installation must have a minimum of a 30-year service life |
Airtight, durable insulation cavity |
- SF
- MH
- MF
Specification | Objective |
---|---|
Separate all foam products from living space with a thermal barrier material (e.g., 1/2" gypsum wallboard) as specified by applicable building code If attic is used only for the service of utilities, foam will be separated from the attic space using a suitable ignition barrier covering or coating according to manufacturer's specifications If attic is used for storage or occupancy, spray foam will be separated from the attic space using a thermal barrier material (e.g., 1/2" gypsum wallboard) as specified by applicable building code and manufacturer specifications If code requirements are unclear, consult local code officials for clarification |
Minimize ignition and combustion potential |
- SF
- MH
- MF
Specification | Objective |
---|---|
Post a dated receipt signed by the installer that minimally includes: Installed insulation type, coverage area, installed thickness, and installed R-value |
Comply with 16 CFR 460.17 and document contract compliance |