No standing water in boiler room
Specifications
- MF
Specification | Objective |
---|---|
Route maintenance blow-down piping to the nearest drain |
No standing water on the mechanical room floor |
- MF
Specification | Objective |
---|---|
Remove debris from drainage system and flush system removing any blockages Verify that drainage system is capable of handling maximum volume of water |
Functioning drainage system that is capable of handling drainage load |
- MF
Specification | Objective |
---|---|
Clean blow-down pit out to handle the volume of water required to sufficiently reduce blow-down temperature for safe discharge Clear blow-down pit connection to the drain system |
Blow-down temperature is within acceptable temperatures and pit drains correctly |
- MF
Specification | Objective |
---|---|
Size sump pit to handle the volume of water required to sufficiently reduce water temperature for safe discharge Verify that sump pump is rated for high-temperature application, operates correctly, and contains a check valve |
Collect and properly discharge water |