Desired Outcome

Safe, compliant, and leak-free system installation that meets the needs of the water consumer without damaging the water system

SF Single Family Site-Built Housing
MH Manufactured Housing
MF Multifamily Housing

Specifications

  • SF
  • MH
  • MF
Specification Objective

Verify current plumbing infrastructure is sufficient to support the installation(s) and is leak-free

Verify adequacy of plumbing

  • SF
  • MH
  • MF
Specification Objective

Select equipment that:

provides the treatment level needed in accordance with the National Association of Corrosion Engineers (NACE TPC 7)

meets the local water standards and requirements

Prevent damage to water distribution system and protect water consumer

  • SF
  • MH
  • MF
Specification Objective

Install system on a level surface where it is protected from freezing and accessible for service

Accessible, freeze-protected installation

  • SF
  • MH
  • MF
Specification Objective

Provide a level working space not less than 30" in length and 30" in width in front of the control side of the appliance

Install appliance and plumbing to allow for inspection, maintenance, and replacement of the appliance and its components, without disturbing other installed equipment, controls, piping, and components, other than what requires repair/replacement

Ensure the appliance can be easily maintained and replaced

  • SF
  • MH
  • MF
Specification Objective

Install system on the cold water side of any water heating system according to manufacturer specifications and applicable codes

If conflict exists between code and manufacturer specifications, apply the more restrictive requirement

Safe, compliant, and durable installation

  • SF
  • MH
  • MF
Specification Objective

Install all electrical wiring in compliance with NFPA 70 and manufacturer specifications

If conflict exists between code and manufacturer specifications, apply the more restrictive requirement

Safe and compliant pump installation

  • SF
  • MH
  • MF
Specification Objective

Install a cut-off valve for the incoming water line and install bypass piping and valve

Allow isolation and bypass of conditioning system

  • SF
  • MH
  • MF
Specification Objective

Store salts for treating the system in a cool and dry environment, not in contact with the floor, and away from metal solids

Prevent corrosion

  • SF
  • MH
  • MF
Specification Objective

Provide occupants/owners with user's manual, warranty information, installation instructions, and installer contact information as well as a copy of the NACE recommendations

Manufacturer supplied information available to occupant