Specification History

SWS Version Created Specification ID Title Specification Objective Rationale Status
Version 2025 05/15/2025 - 12:31 0.0501.1m Commissioning and Testing

Installer shall ensure that the installed equipment matches specifications

Installer shall conduct electrical testing, including but not limited to:
PV string maximum/minimum voltages are confirmed to be within inverter specifications

Conductor insulation test using a megohm meter on all home-run wiring to ensure no leakage currents to earth (Pos-to-GND and Neg-to-GND resistance should be greater than specified in the design)

Operating voltage and polarity of each string measured and documented. Compare voltage measurement to reference value

Grounding resistance is less than specified in the design

Operating current of each string is measured and documented. Compare current measurement to reference value

Installer shall conduct whole system performance test, including but not limited to:

Inverter’s internal power meter and display are confirmed using independent meters (once complete, inverter-displayed power readings can be used for subsequent reporting)

System output under actual conditions is within 5% of expected, calculated performance. Actual power delivery could be from faceplate of inverter or separate power measurement

Check inverter display and operational indicators for status and any error messages. Record operating status

PV array maximum DC power has been confirmed to be within inverter specifications

Installer shall validate that the monitoring system is set up properly and is operational.

Verify proper operation and system performance

The committee combined Commissioning and Testing into a single, comprehensive specification and added more details about verification measures. The new language includes additional details on the process for verifying proper installation and system performance, including specific electrical tests (voltage, current, insulation, and grounding resistance), inverter performance checks, and monitoring system validation. Lettering detail ID was modified to align with correct order. Red Line
Version 2025 10/12/2023 - 16:40 0.0501.1m Testing

Perform electrical tests to verify proper operation and system performance

Tests include open circuit voltage, operating current, resistance of grounding system (should be <25 ohms), and resistance of electrical insulation (should be >1 Megohm)

Measured voltage shall be compared to reference voltage corrected for temperature

Measured current shall be compared to reference current corrected for insolation (sunlight level)

, basic_html

Verify proper operation and system performance

, basic_html
Red Line
Version 2025 10/12/2023 - 16:40 0.0501.1m Testing

Perform electrical tests to verify proper operation and system performance

Tests include open circuit voltage, operating current, resistance of grounding system (should be <25 ohms), and resistance of electrical insulation (should be >1 Megohm)

Measured voltage shall be compared to reference voltage corrected for temperature

Measured current shall be compared to reference current corrected for insolation (sunlight level)

, basic_html

Verify proper operation and system performance

, basic_html
Red Line
Version 2025 10/12/2023 - 16:40 0.0501.1m Testing

Perform electrical tests to verify proper operation and system performance

Tests include open circuit voltage, operating current, resistance of grounding system (should be <25 ohms), and resistance of electrical insulation (should be >1 Megohm)

Measured voltage shall be compared to reference voltage corrected for temperature

Measured current shall be compared to reference current corrected for insolation (sunlight level)

, basic_html

Verify proper operation and system performance

, basic_html
Red Line
Version 2025 10/12/2023 - 16:40 0.0501.1n Cleaning and Disposal 

Clear jobsite of construction waste

Permanently remove all waste materials from job site and recycle or dispose of removed materials in accordance with local and federal law

, basic_html

Old equipment is permanently removed from service, protect the environment, and comply with regulation

, basic_html
Red Line