Durable, weather-proof, and effective, exterior thermal boundary
Specifications
- SF
- MH
- MF
Specification | Objective |
---|---|
Verify that: roof structure is sound and can support additional weight of insulation and roofing materials installation all roof necessary roof penetrations are complete (ventilation, plumbing vents, combustion flues, chimneys, etc.) |
Ensure roof deck can be safely insulated |
- SF
- MH
- MF
Specification | Objective |
---|---|
Remove existing roof covering down to the roof sheathing materials including all fasteners, flashing, etc. Air seal all holes, gaps, seams and penetrations in existing roof deck Replace any damaged or rotten roof sheathing materials Remove any extraneous materials or obstructions from roof deck surface |
Solid, clean, and airtight roof surface |
- SF
- MH
- MF
Specification | Objective |
---|---|
Select sealants that: are compatible with their intended surfaces allow for differential expansion and contraction between dissimilar materials meet the requirements of the applicable fire safety code (e.g., thermal or ignition barriers) |
Select safe, durable, and effective sealants |
- SF
- MH
- MF
Specification | Objective |
---|---|
Install insulation to prescribed R-value without gaps, voids, compressions, misalignments, or wind intrusions and according to manufacturer specifications Offset the seams of multi-layer installations a minimum of 12" |
Install insulation properly |
- SF
- MH
- MF
Specification | Objective |
---|---|
Install a continuous bead of sealant along the entire perimeter of roof deck between insulation layers and roof sheathing and again at subsequent layers of insulation Seal all seams or joints in insulation with gaskets, tapes, or equivalent material Seal all connections, penetrations, corners, etc. |
Prevent air and moisture intrusion under or between insulation layers |
- SF
- MH
- MF
Specification | Objective |
---|---|
Install appropriate flashing and water management systems that direct bulk moisture off of roof and away from building |
Direct bulk moisture away from building |
- SF
- MH
- MF
Specification | Objective |
---|---|
Install new roof covering in accordance with manufacturer specifications and applicable code requirements |
Compliant roof covering installation |
- SF
- MH
- MF
Specification | Objective |
---|---|
Post a dated receipt signed by the installer that minimally includes: Installed insulation type, coverage area, installed thickness, and installed R-value |
Comply with 16 CFR 460.17 and document contract compliance |