Leak free, safe, durable and efficient hot water storage tank
Specifications
- MF
Specification | Objective |
---|---|
Verify current plumbing infrastructure is sufficient to support the installation(s) and is leak-free |
Verify adequacy of plumbing |
- MF
Specification | Objective |
---|---|
Select a water storage tank that: fits in the installation space with required clearances has an R-value of 12.5 or greater |
Select efficient and properly sized water heater |
- MF
Specification | Objective |
---|---|
Install appliance where it: is protected from freezing is accessible for service will maximize efficient operation of the water heating system will minimize distance between tank and primary hot water outlets does not obstruct building egress or access, as required by applicable code (e.g., NFPA 101) |
Select freeze protected, safe, and accessible location that maximizes operation of the water heating system |
- MF
Specification | Objective |
---|---|
Compliant and safe installation |
- MF
Specification | Objective |
---|---|
Provide a level working space not less than 30" in length and 30" in width in front of the control side of the appliance Install appliance and plumbing to allow for inspection, maintenance, and replacement of the appliance and its components, without disturbing other installed equipment, controls, piping, and components, other than what requires repair/replacement Ensure that anode rod is accessible for replacement |
Ensure the appliance can be easily maintained and replaced |
- MF
Specification | Objective |
---|---|
Direct scalding water away from occupants |
- MF
Specification | Objective |
---|---|
If appliance is installed in or above conditioned space or in a location where water damage could occur, install a drain pan according to the requirements of the IRC Drain pan to the exterior of the building |
Prevent water damage from leaking water |
- MF
Specification | Objective |
---|---|
Install a separate water cut-off valve for both the hot and cold water lines and install bypass piping |
Allow isolation and bypass of storage tank |
- MF
Specification | Objective |
---|---|
Install dielectric unions when connecting copper to galvanized steel piping in accordance with the IRC and manufacturer specifications |
Prevent corrosion between dissimilar metals |
- MF
Specification | Objective |
---|---|
Install heat traps on the inlet and outlet piping where not provided by manufacturer |
Reduce thermal loss from convection or siphoning |
- MF
Specification | Objective |
---|---|
Where required, install temperature and pressure gauges on storage tank in an easily visible location |
Easily visible gauges installed |
- MF
Specification | Objective |
---|---|
Permanently remove equipment from job site and recycle or dispose of removed equipment and refrigerant in accordance with local and federal law (e.g., EPA Section 608 of Clean Air Act of 1990) Permanently decommission old equipment |
Old equipment is permanently removed from service, protect the environment, and comply with regulation |
- MF
Specification | Objective |
---|---|
Provide occupants/owners with user's manual, warranty information, installation instructions, and installer contact information |
Manufacturer supplied information available to occupant |