Continuous, contiguous, and safe thermal boundary
Specifications
- MH
Specification | Objective |
---|---|
Verify that installation area is free of: active water leaks, fuel leaks (i.e., gas, oil, propane), and pest intrusions improperly terminated devices (ventilation fans, dryers, plumbing stacks, condensate lines, combustion appliance flues/chimneys, etc.) unshielded high-temperature devices (non-IC rated recessed lights, chimneys, flues, vents, etc.) unless they are zero clearance devices Verify that installation area is: intact, able to support insulation weight and pressure, and air sealed |
Prepare for safe, effective, and airtight installation of dense-packed insulation |
- MH
Specification | Objective |
---|---|
Select sealants that: are compatible with their intended surfaces allow for differential expansion and contraction between dissimilar materials meet the requirements of the applicable fire safety code (e.g., thermal or ignition barriers) are low volatile organic compound (VOC) sealants for use inside the pressure boundary that meet independent testing and verification protocols |
Select safe and effective sealants |
- MH
Specification | Objective |
---|---|
Remove objects from the interior surfaces of the walls being insulated Install durable blocking materials at any openings to the cavity Repair or reattach interior paneling as necessary Set up dust containment enclosure in installation area for all interior installations |
Protect property and workers Contain insulation inside cavity where intended |
- MH
Specification | Objective |
---|---|
Exterior access: Remove the exterior cladding at the insulation access point when feasible If not feasible, drill holes in the exterior siding around the perimeter of the home, parallel to the bottom plate, an equal distance apart, and located under the lowest window sill when possible Neatly cut any vapor retarder installed and minimize air barrier and drainage plane disruption Create an access hole through the sheathing sufficient to access the cavity with fill tube |
Access all wall cavities safely and prepare for access closure |
- MH
Specification | Objective |
---|---|
Install insulation in entirety of each cavity to a density of no more than 1.6 pounds per cubic foot between the interior paneling and any existing insulation Do not overfill any portion of the cavity |
Airtight and continuous pressure and thermal boundary |
- MH
Specification | Objective |
---|---|
Exterior access holes will be closed as follows: Plug holes in sheathing with durable materials and seal with weatherproof exterior sealant Close weather barrier and seal seams with compatible sealant tape Reinstall exterior cladding and secured with mechanical fasteners |
Airtight, durable hole closure |
- MH
Specification | Objective |
---|---|
Post a dated receipt signed by the installer that minimally includes: Installed insulation type, coverage area, installed thickness, minimum settled thickness, installed R-value, and number of bags installed |
Comply with 16 CFR 460.17 and document contract compliance |