Durable, safe, and effective, renewable energy installation
Durable, safe, and effective, renewable energy installation
Specifications
Specification | Objective |
---|---|
Verify current electrical panel and service line infrastructure is in good condition, compliant with codes, and of sufficient electrical capacity (Amps) to accommodate interconnection of solar power. Verify position of spare (unused) breaker or space to install new breaker in panel for solar power interconnection If a roof installation is planned, verify that the roof will support the installation (e.g., dead load, wind load) and that the current roof covering is less than 5 years old. Verify that the type of roof is suitable for solar installation (e.g. not slate or wood shingle). The roof understructure shall be inspected and evaluated for support of PV system. Any reinforcements, such as blocking between rafters, shall be completed before load of PV system is applied If a roof installation is planned, the roof shall be inspected, cleaned and any necessary repairs shall be made Confirm that roof or ground area is suitable to accommodate installation of the indicated size PV system Comply with all federal requirements regarding National Environment Act, Historic Preservation Act and local requirements Verify current electrical panel and service line infrastructure is in good condition, compliant with codes, and of sufficient electrical capacity (Amps) to accommodate interconnection of solar power. Verify the position of spare (unused) breaker or space to install new breaker in panel for solar power interconnection. Any upgrades to the electrical panel or service, such as size and type of circuit breakers, shall be completed before PV system is energized If a roof installation is planned, verify that the roof will support the installation (e.g., dead load, wind load) and that the current roof covering is less than 5 years old. Verify that the type of roof is suitable for solar installation (e.g. not slate or wood shingle). The roof understructure shall be inspected and evaluated for support of PV system. Any reinforcements, such as blocking between rafters, shall be completed before load of PV system is applied If a roof installation is planned, the roof shall be inspected, cleaned and any necessary repairs shall be made If a ground installation is planned, confirm access for installing equipment, suitable slope, suitable stormwater run-off accommodation, and site soil conditions and indicate if any sub-surface infrastructure is present (underground pipes, etc) For roof-mounted or ground-mounted systems, all energized components shall not be accessible to the public through the use of locking hardware, closed wiring raceways or conduit. |
Adequate structural and electrical to support PV install Adequate structural and electrical to support PV install |
Specification | Objective |
---|---|
Design the size of PV system to serve the prescribed load Prepare electrical one line drawing Prepare layout drawings showing location and connections of all equipment Provide list (make, model) of all equipment Design PV system layout to provide safe access around PV modules as required by codes and standards, and required clearances around balance-of-system components such as inverter and switchgear Locate PV Modules to minimize shading factor and maximize solar gain, but not interfere with existing systems or appliance operation (e.g., chimneys, vents, exhaust terminations) Design the size of PV system to serve the prescribed load Prepare electrical one line drawing Prepare layout drawings showing location and connections of all equipment Provide list (make, model) of all equipment Design PV system layout to provide safe access around PV modules as required by codes and standards, and required clearances around balance-of-system components such as inverter and switchgear Locate PV Modules to minimize shading factor and maximize solar gain, but not interfere with existing systems or appliance operation (e.g., chimneys, vents, exhaust terminations) Provide equipment specifications (electrical and physical specifications) of major equipment including PV modules, inverters, metering/monitoring, and other major system components. Specify inverter arrangement (central inverter, string inverter, micro-inverter, DC optimizer) and show all electrical connections on one-line diagram. Include in PV system design any upgrades required for utility meter and utility service to building. |
Maximize PV system performance Maximize PV system performance |
Specification | Objective |
---|---|
Secure approval of design by utility and secure interconnection agreement to operate utility-connected PV system Secure approval of design by utility and secure interconnection agreement to operate utility-connected PV system Determine if utility connection will involve new utility rate schedule and specify. Specify any utility terms regarding net metering of electricity and credit of surplus electricity. |
Obtain utility-connected system interconnection agreement Obtain utility-connected system interconnection agreement |
Specification | Objective |
---|---|
Secure electrical permit to install and operate PV system from Authority Having Jurisdiction (AHJ) (e.g. County building Dept.) |
Obtain required permits for PV installation |
Specification | Objective |
---|---|
Installer shall meet the requirements of AHJ Installer shall meet the requirements of AHJ Installer shall have certification as an installer by the National Board of Certified Energy Professionals (NABCEP) or recognized equivalent certification, training or experience. |
Select qualified installers Select qualified installers |
Specification | Objective |
---|---|
Secure the mounting structures to the roof following manufacturer instructions Install flashing to make all roof penetrations weather-tight and leak-proof using instructions and materials specified by manufacturer Install inverters and disconnects in a safe and accessible location, inverter shall be located in the shade when specified by manufacturer's instructions Install solar panels on the mounting structures according to the manufacturer's instructions
Install flashing to make all roof penetrations weather-tight and leak-proof using instructions and materials specified by the manufacturer If ground mounted, survey subsurface for underground pipes, wires, etc. and install foundation type appropriate for soil conditions and slope Install inverters and disconnects in a safe and accessible location Install solar panels on the mounting structures according to the manufacturer's instructions. |
Watertight, safe, wind-resistant, and compliant roof-mounted equipment installation Watertight, safe, wind-resistant, and compliant roof-mounted equipment installation |
Specification | Objective |
---|---|
The installation shall comply with all applicable codes and standards adopted by Authority Having Jurisdiction, including but not limited to: National Electric Code (NEC) International Residential Code (IRC) IEEE 1547 Standard for Interconnecting Distributed Resources with Electric Power Systems UL 1703 Standard for Flat-Plate Photovoltaic Modules and Panels Manufacturer's installation and operation manuals If conflict exists between code and manufacturer specifications, apply the more restrictive requirement The installation shall comply with all applicable codes and standards adopted by Authority Having Jurisdiction, including but not limited to: National International Residential Code (IRC) IEC 62446-1 for testing and documenting as-built condition of PV system IEEE 1547 Standard for Interconnecting Distributed Resources with Electric Power Systems UL 1703 Standard for Flat-Plate Photovoltaic Modules and Panels UL 2703, Standard for Mounting Systems, Mounting Devices, Clamping/Retention Devices, and Ground Lugs for Use with Flat-Plate Photovoltaic Modules and Panels Manufacturer's installation and operation manuals If conflict exists between code and manufacturer specifications, apply the more restrictive requirement. |
Compliant and safe installation Compliant and safe installation |
Specification | Objective |
---|---|
Install PV Array and Balance of System to allow for inspection, maintenance, and replacement of the PV system components Provide a path that allows the PV modules to be safely accessed without damaging the roof or PV modules Install PV Array and Balance of System to allow for inspection, maintenance, and replacement of the PV system components Provide a path that allows the PV modules to be safely accessed without damaging the roof or PV modules, and access to maintain any ground mounted equipment Comply with codes and consult with fire marshal or fire authority regarding required access. |
System safely accessible for service System safely accessible for service |
Specification | Objective |
---|---|
Install all electrical components according to the NEC and authority having jurisdiction Fasten wires with wire ties and conduit as per design and installation instructions The system shall be connected to the electrical grid at a location and in a method approved by the utility If a conflict exists, the most restrictive rule applies Install all electrical components according to the NEC and Fasten wires with wire ties and conduit as per design and The system shall be connected to the electrical grid at a location and in a method approved by the utility If a conflict exists, the most restrictive rule applies. |
Safely installed interconnected electrical system Safely installed interconnected electrical system |
Specification | Objective |
---|---|
Monitor the system energy delivery for a minimum of 12 months and compare results with predicted energy production
|
Validate system performance
|
Specification | Objective |
---|---|
Provide documentation to the building owner, including: copy of the installation and operation manual electrical diagrams and schematics certificate of inspection and approval system performance benchmark data
|
Facilitate ongoing maintenance and repairs
|
Specification | Objective |
---|---|
Inspect the installation as required by the AHJ Inspect the installation as required by the AHJ Confirm that as-built PV system is as specified (size and number of PV modules, etc). |
Third-party verification of installation safety and operation Third-party verification of installation safety and operation |
Specification | Objective |
---|---|
Perform electrical tests to verify proper operation and system performance Tests include open circuit voltage, operating current, resistance of grounding system (should be <25 ohms), and resistance of electrical insulation (should be >1 Megohm) Measured voltage shall be compared to reference voltage corrected for temperature Measured current shall be compared to reference current corrected for insolation (sunlight level)
Installer shall conduct electrical Conductor insulation test using a megohm meter on all home-run wiring to ensure no leakage currents to earth (Pos-to-GND and
Operating voltage and
Operating current Installer shall conduct whole system performance test, including but not limited to: Inverter’s internal power meter and display are confirmed using independent meters (once complete, inverter-displayed power readings can be used for System output under actual conditions is within 5% of expected, calculated performance. Actual power delivery could be from faceplate of inverter or separate power measurement Check inverter display and operational indicators for status and any error messages. Record operating status PV array maximum DC power has been confirmed to be within inverter specifications Installer shall validate that the monitoring system is set up properly and is operational. |
Verify proper operation and system performance Verify proper operation and system performance |
Specification | Objective |
---|---|
Clear jobsite of construction waste Permanently remove all waste materials from job site and recycle or dispose of removed materials in accordance with local and federal law
Permanently remove all waste materials from |
Old equipment is permanently removed from service, protect the environment, and comply with regulation Old equipment is permanently removed from service, protect the environment, and comply with regulation |
Specification | Objective |
---|---|
Provide occupants/owners with user's manual, warranty information, installation instructions, and installer contact information Provide documentation to the homeowner, including: Provide occupants/owners with user's manual Warranty information and information required to enforce warranties (serial number, Installer contact information, Instructions for cleaning and vegetation management for ground mounted systems Continued monitoring instructions and log-in credentials for the monitoring platform Electrical diagrams and schematics Certificate of inspection and approval System performance benchmark data. |
Manufacturer supplied information available to occupant Manufacturer supplied information available to occupant |
Specification | Objective |
---|---|
The PV modules and inverter shall be warranted by the manufacturer Whole system shall be warranted by the installer for a period of at least 1 year The warranty shall cover defects in materials and workmanship The PV modules and inverter shall be warranted by the manufacturer PV modules shall have manufacturer's "product warranty" covering materials and workmanship for not less than 10 years and "performance warranty" covering at least 80% of nameplate power rating for not less than 25 years. Inverters shall have at least a 10-year warranty by manufacturer Whole system shall be warranted by the installer for a period of at least 1 year.
|
Ensure performance of the installed system Ensure performance of the installed system |