Photovoltaics

Detail ID 0.0501.1
Topic
Baseload – Renewable Energy (Roof Interconnected Photovoltaic)
Subtopic
Electric Supply
Desired Outcome

Durable, safe, and effective, renewable energy installation

Desired Outcome

Durable, safe, and effective, renewable energy installation

Note
SF Single Family Site-Built Housing
MH Manufactured Housing
MF Multifamily Housing

Specifications

Specification Objective

Verify current electrical panel and service line infrastructure is in good condition, compliant with codes, and of sufficient electrical capacity (Amps) to accommodate interconnection of solar power.  Verify position of spare (unused) breaker or space to install new breaker in panel  for solar power interconnection

If a roof installation is planned, verify that the roof will support the installation (e.g., dead load, wind load) and that the current roof covering is less than 5 years old.  Verify that the type of roof is suitable for solar installation (e.g. not slate or wood shingle). The roof understructure shall be inspected and evaluated for support of PV system.  Any reinforcements, such as blocking between rafters, shall be completed before load of PV system is applied

If a roof installation is planned, the roof shall be inspected, cleaned and any necessary repairs shall be made

Confirm that roof or ground area is suitable to accommodate installation of the indicated size PV system

Comply with all federal requirements regarding National Environment Act, Historic Preservation Act and local requirements

Verify current electrical panel and service line infrastructure is in good condition, compliant with codes, and of sufficient electrical capacity (Amps) to accommodate interconnection of solar power. Verify the position of spare (unused) breaker or space to install new breaker in panel for solar power interconnection. Any upgrades to the electrical panel or service, such as size and type of circuit breakers, shall be completed before PV system is energized

If a roof installation is planned, verify that the roof will support the installation (e.g., dead load, wind load) and that the current roof covering is less than 5 years old. Verify that the type of roof is suitable for solar installation (e.g. not slate or wood shingle). The roof understructure shall be inspected and evaluated for support of PV system. Any reinforcements, such as blocking between rafters, shall be completed before load of PV system is applied

If a roof installation is planned, the roof shall be inspected, cleaned and any necessary repairs shall be made

If a ground installation is planned, confirm access for installing equipment, suitable slope, suitable stormwater run-off accommodation, and site soil conditions and indicate if any sub-surface infrastructure is present (underground pipes, etc)

For roof-mounted or ground-mounted systems, all energized components shall not be accessible to the public through the use of locking hardware, closed wiring raceways or conduit.

Adequate structural and electrical to support PV install 

Adequate structural and electrical to support PV install

Specification Objective

Design the size of PV system to serve the prescribed load

Prepare electrical one line drawing

Prepare layout drawings showing location and connections of all equipment

Provide list (make, model) of all equipment 

Design PV system layout to provide safe access around PV modules as required by codes and standards, and required clearances around balance-of-system components such as inverter and switchgear

Locate PV Modules to minimize shading factor and maximize solar gain, but not interfere with existing systems or appliance operation (e.g., chimneys, vents, exhaust terminations) 

Design the size of PV system to serve the prescribed load

Prepare electrical one line drawing

Prepare layout drawings showing location and connections of all equipment

Provide list (make, model) of all equipment

Design PV system layout to provide safe access around PV modules as required by codes and standards, and required clearances around balance-of-system components such as inverter and switchgear

Locate PV Modules to minimize shading factor and maximize solar gain, but not interfere with existing systems or appliance operation (e.g., chimneys, vents, exhaust terminations)

Provide equipment specifications (electrical and physical specifications) of major equipment including PV modules, inverters, metering/monitoring, and other major system components. Specify inverter arrangement (central inverter, string inverter, micro-inverter, DC optimizer) and show all electrical connections on one-line diagram. Include in PV system design any upgrades required for utility meter and utility service to building.

Maximize PV system performance 

Maximize PV system performance

Specification Objective

Secure approval of design by utility and secure interconnection agreement to operate utility-connected PV system

Secure approval of design by utility and secure interconnection agreement to operate utility-connected PV system

Determine if utility connection will involve new utility rate schedule and specify. Specify any utility terms regarding net metering of electricity and credit of surplus electricity.

Obtain utility-connected system interconnection agreement

Obtain utility-connected system interconnection agreement

Specification Objective

Secure electrical permit to install and operate PV system from Authority Having Jurisdiction (AHJ) (e.g. County building Dept.)

Obtain required permits for PV installation

Specification Objective

Installer shall meet the requirements of AHJ

Installer shall meet the requirements of AHJ

Installer shall have certification as an installer by the National Board of Certified Energy Professionals (NABCEP) or recognized equivalent certification, training or experience.

Select qualified installers

Select qualified installers

Specification Objective

Secure the mounting structures to the roof following manufacturer instructions 

Install flashing to make all roof penetrations weather-tight and leak-proof using instructions and materials specified by manufacturer

Install inverters and disconnects in a safe and accessible location, inverter shall be located in the shade when specified by manufacturer's instructions

Install solar panels on the mounting structures according to the manufacturer's instructions

SecureIf roof mounted, secure the mounting structures to the roof following manufacturer instructions

Install flashing to make all roof penetrations weather-tight and leak-proof using instructions and materials specified by the manufacturer

If ground mounted, survey subsurface for underground pipes, wires, etc. and install foundation type appropriate for soil conditions and slope

Install inverters and disconnects in a safe and accessible location,. The inverter shall be located in the shade when specified by manufacturer's instructions, if possible

Install solar panels on the mounting structures according to the manufacturer's instructions.

Watertight, safe, wind-resistant, and compliant roof-mounted equipment installation

Watertight, safe, wind-resistant, and compliant roof-mounted equipment installation

Specification Objective

The installation shall comply with all applicable codes and standards adopted by Authority Having Jurisdiction, including but not limited to: 

National Electric Code (NEC

International Residential Code (IRC

IEEE 1547 Standard for Interconnecting Distributed Resources with Electric Power Systems 

UL 1703 Standard for Flat-Plate Photovoltaic Modules and Panels 

Manufacturer's installation and operation manuals 

If conflict exists between code and manufacturer specifications, apply the more restrictive requirement 

The installation shall comply with all applicable codes and standards adopted by Authority Having Jurisdiction, including but not limited to:

National ElectricElectrical Code (NEC)

International Residential Code (IRC)

IEC 62446-1 for testing and documenting as-built condition of PV system

IEEE 1547 Standard for Interconnecting Distributed Resources with Electric Power Systems

UL 1703 Standard for Flat-Plate Photovoltaic Modules and Panels

UL 2703, Standard for Mounting Systems, Mounting Devices, Clamping/Retention Devices, and Ground Lugs for Use with Flat-Plate Photovoltaic Modules and Panels

Manufacturer's installation and operation manuals

If conflict exists between code and manufacturer specifications, apply the more restrictive requirement.

Compliant and safe installation

Compliant and safe installation

Specification Objective

Install PV Array and Balance of System to allow for inspection, maintenance, and replacement of the PV system components

Provide a path that allows the PV modules to be safely accessed without damaging the roof or PV modules

Install PV Array and Balance of System to allow for inspection, maintenance, and replacement of the PV system components

Provide a path that allows the PV modules to be safely accessed without damaging the roof or PV modules, and access to maintain any ground mounted equipment

Comply with codes and consult with fire marshal or fire authority regarding required access.

System safely accessible for service

System safely accessible for service

Specification Objective

Install all electrical components according to the NEC and authority having jurisdiction

Fasten wires with wire ties and conduit as per design and installation instructions

The system shall be connected to the electrical grid at a location and in a method approved by the utility

If a conflict exists, the most restrictive rule applies

Install all electrical components according to the NEC and authority having jurisdictionAHJ

Fasten wires with wire ties and conduit as per design and installationmanufacturer's instructions

The system shall be connected to the electrical grid at a location and in a method approved by the utility

If a conflict exists, the most restrictive rule applies.

Safely installed interconnected electrical system

Safely installed interconnected electrical system

Specification Objective

Monitor the system energy delivery for a minimum of 12 months and compare results with predicted energy production

Monitor the system energy delivery for a minimum of 12 months and compare results with predicted energy production

Validate system performance

Validate system performance

Specification Objective

Provide documentation to the building owner, including:

copy of the installation and operation manual

electrical diagrams and schematics

certificate of inspection and approval

system performance benchmark data

Provide documentation to the building owner, including:

copy of the installation and operation manual

electrical diagrams and schematics

certificate of inspection and approval

system performance benchmark data

Facilitate ongoing maintenance and repairs

Facilitate ongoing maintenance and repairs

Specification Objective

Inspect the installation as required by the AHJ

Inspect the installation as required by the AHJ

Confirm that as-built PV system is as specified (size and number of PV modules, etc).

Third-party verification of installation safety and operation

Third-party verification of installation safety and operation

Specification Objective

Perform electrical tests to verify proper operation and system performance

Tests include open circuit voltage, operating current, resistance of grounding system (should be <25 ohms), and resistance of electrical insulation (should be >1 Megohm)

Measured voltage shall be compared to reference voltage corrected for temperature

Measured current shall be compared to reference current corrected for insolation (sunlight level)

PerformInstaller shall ensure that the installed equipment matches specifications

Installer shall conduct electrical teststesting, including but not limited to:
PV string maximum/minimum voltages are confirmed to verify proper operationbe within inverter specifications

Conductor insulation test using a megohm meter on all home-run wiring to ensure no leakage currents to earth (Pos-to-GND and system performance

Tests include open circuit voltage, operating current,Neg-to-GND resistance of grounding system (should be <25 ohmsgreater than specified in the design),

Operating voltage and resistancepolarity of electrical insulation (should be >1 Megohm)

Measuredeach string measured and documented. Compare voltage shall be comparedmeasurement to reference voltage corrected for temperaturevalue

MeasuredGrounding resistance is less than specified in the design

Operating current shall be comparedof each string is measured and documented. Compare current measurement to reference current correctedvalue

Installer shall conduct whole system performance test, including but not limited to:

Inverter’s internal power meter and display are confirmed using independent meters (once complete, inverter-displayed power readings can be used for insolation (sunlight levelsubsequent reporting)

System output under actual conditions is within 5% of expected, calculated performance. Actual power delivery could be from faceplate of inverter or separate power measurement

Check inverter display and operational indicators for status and any error messages. Record operating status

PV array maximum DC power has been confirmed to be within inverter specifications

Installer shall validate that the monitoring system is set up properly and is operational.

Verify proper operation and system performance

Verify proper operation and system performance

Specification Objective

Clear jobsite of construction waste

Permanently remove all waste materials from job site and recycle or dispose of removed materials in accordance with local and federal law

ClearUpon completion of installation, clear jobsite of construction waste

Permanently remove all waste materials from job sitejobsite and recycle or dispose of removed materials in accordance with local and federal lawrequirements.

Old equipment is permanently removed from service, protect the environment, and comply with regulation

Old equipment is permanently removed from service, protect the environment, and comply with regulation

Specification Objective

Provide occupants/owners with user's manual, warranty information, installation instructions, and installer contact information

Provide documentation to the homeowner, including:

Provide occupants/owners with user's manual

Warranty information and information required to enforce warranties (serial number, warrantydate of installation) upon transfer of manufacturer equipment warranties for all components such as PV modules and inverters

Installer contact information, installation instructionscontact information for emergency contacts (utility company, fire department), suppliers of services and installer contact informationspare parts

Instructions for cleaning and vegetation management for ground mounted systems

Continued monitoring instructions and log-in credentials for the monitoring platform

Electrical diagrams and schematics

Certificate of inspection and approval

System performance benchmark data.

Manufacturer supplied information available to occupant

Manufacturer supplied information available to occupant

Specification Objective

The PV modules and inverter shall be warranted by the manufacturer

Whole system shall be warranted by the installer for a period of at least 1 year

The warranty shall cover defects in materials and workmanship

The PV modules and inverter shall be warranted by the manufacturer

PV modules shall have manufacturer's "product warranty" covering materials and workmanship for not less than 10 years and "performance warranty" covering at least 80% of nameplate power rating for not less than 25 years. Inverters shall have at least a 10-year warranty by manufacturer

Whole system shall be warranted by the installer for a period of at least 1 year.

The warranty shall cover defects in materials and workmanship

Ensure performance of the installed system

Ensure performance of the installed system

View Sub-Topic:
Electric Supply